Tasks completed in previous 90 days:
- Ceilings, paint and tile to be installed
- Millwork, fixtures and flooring under construction
- Kitchen and cafeteria complete
- HVAC and controls under construction
- New track and turf field installed
- Sidewalks and landscaping under construction
Upcoming tasks:
- Final paint and wall trim out
- Complete millwork and fixtures
- Complete marker and tack boards, room signage
- Flooring installed and resurfaced wood floors
- Final cleaning of building
- Furniture assembly and installation beginning in May
- Landscaping
- Network and final punch