Tasks Completed in the last 90 days:
- Site Drives and parking complete
- Steel Structure and Roof installed
- Walls, Windows and Brick under construction
- Storm Shelter complete
- Permanent Power and Conditioned Air installed
Upcoming tasks:
- Kitchen equipment
- Millwork, Fixtures, Ceilings and Final Paint coat
- Flooring to be complete
- HVAC complete, Balancing in progress
- Landscaping in progress