      Updates

      • Tasks Completed in the last 90 days:

        • Site utilities (Storm , Sanitary, Electric, Fiber, Water and Gas) ongoing
        • Geowell drilling
        • Site grading and fire lanes began
        • Auger cast piles/piers started in all areas

        Upcoming tasks:

        • Geowells to be completed
        • Complete fire lanes
        • Drilling foundation piers/piles to be completed
        • Grade beams will begin
        • Underslab utilities will begin
        • Slab on grade to begin
        • Will begin erecting steel in late summer