Tasks completed in the previous 90 days:
- Drop ceiling panels in admin, kitchen, and grid for cloud ceilings in cafeteria
- Plumbing fixtures in admin, kitchen/dining
- Kitchen equipment starting
- Curtain walls are ongoing with glazing
- Courtyard turf and landscaping starting
- Door hardware install ongoing
- Tape/bed/paint ongoing
- Cabinets/millwork starting
- Flooring installation ongoing
- Gym interior is ongoing with plumbing installation started
- Fencing, irrigation, landscape, and other site work started
Upcoming Tasks:
- Canopy installation has begun
- Installation of carpet will begin in the admin area
- The ceiling grid is being installed throughout
- IDF and MDF rooms are being completed by mid-late May
- Millwork is being installed throughout
- Tile in all areas is ongoing
- Overhead inspections are ongoing and the ceiling will be completed
- The ceilings in the cafeteria have begun
- Site work is ongoing. Fencing, irrigation etc
- Finishes are ongoing throughout the building
- Elevator to be installed
- Finishes are ongoing throughout
- Solar Panels are being installed on the roof