Tasks completed in the previous 90 days:
- Utilities under slab
- Technology site utilities
- Slab on grade by
- Geothermal well fields completed
- Paving around site (Parking lots and fire lanes)
- Columns/beams Area 1/4
Upcoming Tasks:
- CMU walls for gym will be installed mid December
- Steel structure for the main building
- Joist and decking for gym
- Prefab panels will be installed by mid-February
- Framing/sheathing/waterproofing walls in courtyard will begin at the end of February
- Roofing will begin February.