Tasks Completed in the last 90 days:
- Concrete sidewalks and retaining walls are complete
- Practice field subgrade is complete
- Installing electric, data, and fire protection systems
- Insulated the roof and walls
- Installed all utility lines to the building
- Completed roof, exterior sheathing and waterproofing
Upcoming tasks:
- Complete steel building erection
- Install roof frame, decking, and wall panels
- The remaining grade beam and slab on grade
- Metal framing and mechanical, electrical, and plumbing rough in
- Practice field drainage and field preparation