DHS Multipurpose Facility

      Updates

      • Tasks Completed in the last 90 days:

        • Concrete sidewalks and retaining walls are complete 
        • Practice field subgrade is complete
        • Installing electric, data, and fire protection systems
        • Insulated the roof and walls
        • Installed all utility lines to the building
        • Completed roof, exterior sheathing and waterproofing

        Upcoming tasks:

        • Complete steel building erection 
        • Install roof frame, decking, and wall panels
        • The remaining grade beam and slab on grade 
        • Metal framing and mechanical, electrical, and plumbing rough in
        • Practice field drainage and field preparation