Tasks Completed in the last 90 days:
- Site clearing and grading
- Construction trailers, laydown yard, and site fencing
- Underground utilities began
- Installing geothermal wells
- Constructing building pads
Upcoming tasks:
- Rough grading to be completed
- Continue underground utilities
- Continue geothermal wells
- Construct building piers and grade beams
- Install fire lanes around the building pad
- Concrete foundation and slab